2017-09-05 Sprint 1 Entry

2017-09-05 Sprint 1 Entry

Date

Sep 5, 2017

Attendees

  • @Medha Parlikar (Unlicensed)

  • @Michael Stay (Unlicensed)

  • @Chris Kirkwood-Watts

  • @Griff McClellan (Unlicensed)

  • @Timm Schäuble

  • Kent Shakima

  • @Former user (Deleted) (Invited)

Goals

  • Define plan for Sprint 1

Discussion items

 

Time

Item

Who

Notes

Time

Item

Who

Notes

15 min

Process

@Medha Parlikar (Unlicensed)

  • Initial Sprint will be 2 weeks in duration

  • JIRA functionality walk through, Q&A

  • Determine story point process and document

  • Determine when/how we will have standup

  • Kent prefers to move Contracts over to Rholang.

 30

Entry 

 @Medha Parlikar (Unlicensed)

  •  Story point tickets

  • 1,2,3,5,8,13,21

  • 1 - approx 1 hour

  • 2 points - 4 hours

  • 5 - 1 day

  • 8 - 3 days

  • 13 - 1 week

  • 21 - 2 weeks of work

  • Confirm Rosette work

  • Flesh out tickets if needed

  • Capture action items on when sprint should start.