Date

Participants

Goals

Create a plan in tickets for SRE work for the next 12 weeks.

Discussion topics

Item

Notes

Happy path to Mercury

  • RCHAIN-3381 - Getting issue details... STATUS (2 sprints) and discussions to confirm contracts needed for tests in networks #2 and #3

  • RCHAIN-3382 - Getting issue details... STATUS and RCHAIN-3383 - Getting issue details... STATUS to be done in parallel (2 sprints)

Future sprint sketch

Sprint 29

  • 3381

  • Maintain pubnet

  • Release software

  • Work on whiteblock

Sprint 30

  • finish 3381

  • Maintain pubnet

  • Release software

  • Work on whiteblock

  • Run tests in hardening network

Action items

  • Kelly Foster look at time off calendar (late-June Adam, Aug. Tomáš)
  •  

Decisions