Time | Item | Who | Notes |
---|
5 min | Updates from May 30 meeting | Medha | - CI improvement work and status
- Early performance test
- New cadence for node testing with community
|
5 min | Node 5 |
| - Release date is July 12th (thanks to holiday)
- Sprint 10 + 11 are part of the release.
- Other items?Consensus is on track. Integrating with RSpace
- Getting contracts into the code base.
|
10 min | Network |
| - This week's community node test revealed problems with the network. What is being done and by when to support next week's community test?. Pawel is working to identify the problem & crafting a solution. The goal is to deliver a version of rnode that has debugging and logging in at a minimum, if not a fix for the problem.
|
5 min | RSpace |
| |
30 min | Node 6 |
|
|