Item
Notes
Timeline
Jan. delivery
Goal of done before Christmas holiday
Discussion of process
Draft table of contents
Review of the table of contents
Reviewers: dev team and community
Week of Nov. 5
1st draft complete by Nov. 5
Revisions 2nd draft complete Nov. 26
Final review Review period Dec. 3 for 1 week
Host 1-2 office hour sessions
Revisions Revision work Dec. 10-17
Publication by Jan. 4
Tools
Plan to use MD
Plan to write in rchain/rchain